  1. Go to Jira Settings → Projects:

    Image RemovedImage Added

  2. Then you need to choose Team-managed project you’d like to manage inside ActivityTimeline and click on the title:

  3. Once you open it, click on Project Settings → Issue types

  4. There you will need to add ‘Start date’ & ‘Due date’ fields as Context fields to every issue type you have in your project:

  5. Once you have this setup on all your Team-managed projects, go to ActivityTimeline Configuration-> Jira integration → Team-Managed Projects Settings → Choose ‘Re-use Jira’s standard Start/Due date fields’ → Click ‘Update’:

  6. Finally, you’re all set, now you can plan your Team-Managed project both from ActivityTimeline and it’ll be displayed in Jira and vice versa.

...

In a nutshell, that’s it, you can go to ‘Plan’ view and drag’n’drop or resize items without any errors. System will be updating the assignee field in Jira, but not ‘Start/End’ dates.

Hopefully this was useful to you!

Feel free to contact us if you have any questions or comment: support@reliex.com.

...

(question) Frequently Asked Question. Read more.

📰 Helpful tips in our Blog.

?? Questions? Contacts Us.

🤝 Contact details for Solution partners.