Example: There are 4 people in the team: Frank, Anna, Bob, and John, they work 8 hours a day, 40 hours a week, their total capacity = 160h. Frank & Bob are both booked for 50% of their time for this week (20 hours), while Anna is 100% booked (40 hours) and John is booked for 25% of his week (2 hours), additionally there 4 tasks (5 hours each) on the team panel, that is still to be assigned to the team members.
In this scenario, Team Total Workload equals of all work scheduled on team members: Frank (20h) + Anna (40h) + John

...

Example: There are 3 users in the team: Bob, Frank, and Anna, each has a personal capacity (involvement) of 8 hours per day, meaning that the total capacity for the team is 24 hours/day or 240h for 2 weeks sprint.
This means that their manager can assign up to 180h worth of tasks to their team for a span of 2 weeks.

...