Team Detailed Workload Report  provides detailed summary of team’s workload.

It shows the amount of scheduled work per project key (project key is a short project code) per team. 

Color corresponds to the team's workload in a given week (column). Yellow - underloaded, green - nominal, red - overloaded.

To generate Team Detailed Workload Report follow the steps:

  1.  Navigate to Reports page and find the desired report in the list:      
            
     

       2. Select the display units the data to be grouped by – day, week or month.

       3. Select the First Month which the report is supposed to be started from

    • the default value is Current Month, other available options are: Previous Month, Current Month and Next Month up to one year.

      4.  Select a Period the report is to be generated for.

    • the default value is 1 month, options are from 1 month to 12 months.

      5. Select a Team the report is to be generated for.

  • the default value is Current selected Team on Dashboard.

      6. Generate report in web or Excel format:

            

→ Team Detailed Workload Report is generated. It is similar to the Team Summary Workload Report but also contains project level details.

             