Planned vs Actual Report

This type of report provides a summary of JIRA tickets, time estimates (original and remaining), time spent already on the tickets, and ticket status.

To generate a Planned vs Actual Report follow the steps:

1. Navigate to the Reports page and find the desired report in the list: 

 

       

2. Specify type of the report (Issue, Project, or Epic); month, period (default value = previous month), and team (default value = Current team that is displaying on the Dashboard).

  1. You can also add additional custom fields to be shown in the report to add some additional information:

4. Check 'Exclude Time of Sub-tasks from Time of Main Task' or leave it unchecked

  • if an option is checked, the system will not aggregate the estimates / logged time from the sub-tasks and provide a value of time estimated and time spent of a main task

  • if an option is not checked, the system will aggregate the estimates / logged time from all the sub-tasks of a main task.     

5. Generate Report in Web or Excel format:

 

→ Planned vs Actual Report opens in the selected format. 

A report represents the collected data about JIRA tickets, a person who was the last assignee, Start and End Dates, Original and Remaining Estimates, Time Spent (logged work), Issue Summary and Status.

The status of a ticket is marked with different colors:

  • green - OK status, means that Time Spent + Remaining Estimate = Original Estimate

  • yellow - OVERESTIMATED status, means that Time Spent + Remaining Estimate < Original Estimate

  • red - UNDERESTIMATED status, means that Time Spent + Remaining Estimate > Original Estimate

You can learn more about this report in the video below:

https://youtu.be/xa60zWGwqTY?si=vO1l80QiPVXB7vAG

 

 