Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

...

ActivityTimeline add-on provides everybody who has access to a specific team

...

timeline the ability to see the workload or availability for each person and

...

the whole team. 

...

The workload indicator is displayed in the

...

planner view below each person's name and shows the amount of work scheduled for that person for a specific period

...

What tickets are calculated in the Workload Indicator?
Tickets with remaining or daily estimates.

Workload Indicator

...

Color

Workload indicator has eight main colors to help managers and teams have

...

better visibility of a person's availability:

...

  • blue - out of the office;

...

  •  Day Off, Vacation, Sick Leave, or Holiday is scheduled on a user

...

  • yellow - workload is not enough (less than 50% h/day) and some additional tickets can be added to a timeline

...

  • olive - workload is not enough (between 50-88% h/day) and some additional tickets can be added to a timeline

...

  • green - workload is enough (between 88-100% h/day), no more tickets can be scheduled on a timeline

  • light

...

  • red - a person is overloaded (between 100-125% h/day) and some tickets have to be re-scheduled for another day

  • red - a person is overloaded (more than 125% h/day) and some tickets have to be re-scheduled for another day

...

  • purple - Day Off, Vacation, Sick Leave, or Holiday is assigned on Logged time or weekend

  • grey -  workload is "0" h/day; no workload is displaying on that day

...

  •    

...

Image Added
Panel
panelIconIdatlassian-note
panelIcon:note:
bgColor#FFFFFF

From version 9.6.4 onwards, it is possible to customize the data range for workload indicators by accessing the "Workload Indicator Color Range Customization" option under the Configurations - Workload Indicator settings.

Image Added

The workload indicator view depends on a current calendar view, users' involvement, and Work hours in a day. If look at a default one-week scope view

...

, a user will see his availability for each day in

...

the current week:

...

Image Added

If the scope is changed to Two Weeks, Month - Weekly, then a different view will load

...

             Image Removed

Workload Calculation

The workload is calculated based on the estimated hours for specific tickets scheduled on a person's timeline. 

  • for a full-time involvement, the workload should be 8 hours per day. It means that a manager can schedule JIRA tickets with total Remaining Tme Estimate = 8 hours. If the total remaining time estimate for all scheduled tickets exceeds 8 hours, the person is overloaded and a manager should fix his/her workload. To change and fix this, drag and drop this task on another day.

  • for a part-time involvement, the workload should correspond to the number of working hours specified in Configuration settings. If a person is a contractor with 4 hours workload, his or her manager should not schedule JIRA tickets with total remaining time estimate more than 4 hours per one day.         

To see the remaining time estimate for a specific ticket, mouse-over that ticket in Issues Panel, timeline panel or click on it to open JIRA view.

...

with the aggregated numbers per week, and month.

Workload Calculation Algorithm

Workload Calculation mode can be specified by ActivityTimeline administrator

...

in the main configurations page. There are two ways

...

how a workload can be calculated:

Image Added

Balance Mode

Liquid Mode

Balance mode evenly distributes hours for a set period.
This is a default calculation mode.

If a task is estimated for 10 hours, and a manager schedules it for 2 days, the system will automatically schedule 5 hours per each day for that task

The liquid mode will help you to plan the workload according to default involvement of a user.

If a task is estimated for 10 hours, and a manager schedules it for 2 days, the system will automatically put all hours upfront. It's a move

...

convenient way of scheduling

  • for a full-time worker a task will be scheduled for 8h for the first day, but still appear stretched to 4 days in a timeline

  • for a part-time worker a task will be scheduled for 4h for the first two days, but still appear stretched for 4 days in a timeline 

Example with one task:

...

Image Added

Example with one task:

Image Added

Example with overlapping tasks: 10h task is evenly spread out for two days and 5h task is added to firsd day

...

Image Added

Example with

...

  • Change Workload Calculation Algorithm value from BALANCE to LIQUID.     

 Image Removed

  • click Update and go back to Dashboard  

...

Workload Indicator available options:

...

for Future and Past Days 

...

for Future Days including current day

...

Worklogs & Workload Mode

...

N/A

...

  • "Exclude past days/weeks/days and today from distributing remaining estimate" option set by default

  • "Treat Booking items as worklogs in the past" option

...

/wiki/spaces/ACTS/pages/193527811

...

  • "Distribute remaining estimate into past days" option

...

  • "Exclude past days/weeks/days and today from distributing remaining estimate" option

...

/wiki/spaces/ACTS/pages/193527811

...

  • "Distribute remaining estimate into past days" option

...

  • "Exclude past days/weeks/days and today from distributing remaining estimate" option

Worklogs & Workload Mode

This setting is useful when people log work and the remaining time estimate decreases over time.

To reflect proper planning the remaining estimate is excluded and not spreaded on the past period of time. Keeping this setting will allow people to track their time in a JIRA ticket more precisely.

Indicators is displaying people's actual workload based on tasks remaining estimates in the future and logged hours in the past.

A team member has 15 hours of work from Monday till Friday. 9th of May is the current date and 7th and 8th of May have already passed. The remaining time estimate of 15 hours should not be allocated to the period in the past since nobody will jump to a past date and perform the remaining hours of work.
Image Removed

Estimation and Logged hours

Issue is estimated to 35 hours. Monday and Tuesday are a past days - they are not taken into account.
Estimated hours are pulled upfront to the rest of scheduled period - from Wednesday (current day) till Friday.
Image Removed

If user log work on Monday and Tuesday (8 hours each day) than estimation of the issue automatically decrease.  Image Removed

Estimation and Overdue tasks

Indicator will show star (*) symbol that some estimated task is overdue in the past period .

...

Indicator will show overdue estimated task with logged time as number with star symbol (*) in the past period.
Image Removed

 Workload Mode 

overlapping tasks: the system covered 8h working day with 5h task that should be done for the first day; time of 10h task is allocated according to the user's involvement

...

Image Added

Individual Indicator Modes

There are four main indicator modes available:

  1. Workload

  2. Number of Issues

  3. Availability

  4. Worklogs and Workload

Image Added
Note

It is important to remember that the time tracking mode directly influences on the workload/ availability calculation algorithm.

Please review Time Tracking Modes Documentation to choose the correct mode for your usecase.

Note

If you are utilizing story points for estimation, it's important to select the 'Users do not log time' option in the Time Tracking mode, even if your team members are tracking their time. Story points represent a measure of effort and function differently from hourly estimations. These points remain constant regardless of the time logged by users, and our system automatically distributes them across the entire duration of the task.

To ensure that story points are accurately factored into the workload calculations, please make sure to set up the Story Points Conversion Factor.

Workload Mode 

Indicators will display people's workload based on remaining

...

estimates of tasks

...

"Exclude past *period from distributing remaining estimate" option for Workload Mode:

The remaining time estimate of 16 hours should not be allocated to the period in the past since nobody will jump to a past date and perform the remaining 8 hours of work. 

...

, daily estimates, and events.

“If worked time is tracked”:

The indicator shows only workload with a distributed remaining estimate for the future period without

...

showing logged time in the past.

...

The remaining estimate from the past (ex.:

...

Monday

...

) shifted to future days:

...

*Available options: days/weeks/days and today on Workload Indicator Settings (Legacy) page.

"Distribute remaining estimate into past days" option for Workload Mode:

...

Image Added

“If worked time isn’t tracked”:

An indicator shows distributed along the durations of the workload of the tasks (The remaining estimates, daily estimates, and events) without showing a logged time: 

...

Image Added

Number of Issues Mode

Indicators will display how many issues are assigned to a user for the day, week, or month.

Image Added

Availability Mode

Indicators will display people's availability based on

...

involvement, remaining estimates, and daily estimates of scheduled tasks

...

and events

“If worked time is tracked”:

The indicator shows only

...

how many hours are still available for the specified day, week, or month for the future period without

...

showing logged time in the past

...

or availability. The indicator will show overdue estimated tasks with logged time as a number with a star symbol (*) in the past period (ex.: on Monday).

...

The remaining estimate from the past (ex.:

...

Monday) shifted to future days

...

*Available options: days/weeks/days and today on Workload Indicator Settings (Legacy) page.

"Distribute remaining estimate into past days" option for Availability Mode:

...

:

Image Added

“If worked time isn’t tracked”:

An indicator shows how many hours are still available for the specified day, week, or month taking into account the remaining estimates of the tasks allocated to past and future days as well without

...

showing a logged time:

...

Image Added

Worklogs & Workload Mode

This setting is useful when users log work and the remaining time estimate decreases over time.

To reflect proper planning the remaining estimate is excluded and not spread over the past period.

Info

Indicators display people's actual workload based on tasks remaining estimates in the future and logged hours in the past.

Example

The user has a task assigned from Monday to Friday, he logs work on Monday and Tuesday (8 hours each day) then the remaining estimate of the issue automatically decreases. The indicator will show a number of hours logged for the past (8 hours on Monday, 8 hours on Tuesday) and workload for the future based on the remaining estimate (6.7 hours Wednesday-Friday):

Image Added

Additional Settings

Exclude Past Days

If ActivityTimeline administrator wants to exclude any past days from the remaining time estimate distribution in Workload and Availability modes as well, he or she can configure this in Configuration:

  1. Go to

...

  1.  Configuration tab

...

  1.  Workload Indicator page

...

  1. Workload & Availability Modes section

  2. Select the desired value:

  • Distribute the remaining estimate into the past days 

    (not recommended)

  • Exclude past days/weeks/days and today from distributing the remaining estimate

...

3. Click Update.

...

This setting ensures that the system will not spread the remaining time estimate across the past period and the current date

...

Booking calculation in Workload Indicator

.

This works with both BALANCE and LIQUID workload calculation modes.

Estimation and Overdue tasks
Status
colourRed
title(Deprecated from v. 9.8.4)

The indicator will show a star (*) symbol notifying that some estimated task is overdue in the past period and isn’t completed.

Image Added

The indicator will show a star symbol (*) near logged hours in the past if there is an overdue estimated task in the past and logged hours.

Image Added

Booking calculation in Workload and Worklogs Mode

ActivityTimeline allows to to track time spent not only on Jira issues.The "Treat Booking items as worklogs

...

" option

...

determines how worklogs are calculated in the past days.

...

Workload indicators will display

...

users'

...

actual workload based on

...

the bookings' estimates for the future and

...

treat them as worklogs when they are in the past.

...

Image Added

To set an option:

  1. Go to

...

  1.  Configuration tab → Timesheets Configuration

  2. "Treat Booking items as worklogs

...

  1. " checkbox is enabled

...

Learn more about how to track time on not Jira Issues

Workload Indicator and Custom Events

...

As already mentioned previously the system calculates not only the

...

workload/ availability based on remaining estimates of the tasks but also understands the Booking, Days Off, Vacation, and other custom events.

If a manager schedules a ticket estimated for 5 hours for Wednesday and Thursday, and a person has already booked a vacation or day off for Wednesday, the system will put all 5 hours on Wednesday. This case involves Worklog & Workload, Workload, and Availability Modes. 

...

Image Added

To fix this, resize the task and move it up to Friday →

...

The system will put in 5 hours of work on

...

Friday, and nothing on

...

Thursday.

The same is true with weekends.

Switch back to Two Weeks scope → the system will equally split 20 hours of work on Wednesday-Friday and Monday, keeping nothing on Saturday and Sunday. 

...

 

Tip

Weekends are also configurable. By default, Sunday and Saturday are specified as non-working days.

But one can set Saturdays as working days and such, in Configuration -> Workload Indicator Settings (Legacy) page.

Configure Working Days

...

Image Added

Working Days Configuration

To change the default weekend options follow the steps:

  1. Navigate

...

  1. to the Configuration tab

...

  1. → Workload Indicator page

...

  1. → Work Time section.

  2. Check/uncheck the days you wish to be working days in the corresponding option   

...

  1. Image Added

  2. Edit the number of working hours per day Work hours in day option.

...

  1. Press the Update button.        

...

Indicators for Total Team Workload

The system allows each team member to see the total team workload, total team availability for a specific period of time and switch capacity mode. This information is available at the bottom panel: 

         Image Removed

Total Team Worklogs is a total sum of logged hours for the whole team in a current week. The value changes when switching the calendar view. Available in Worklogs & Workload Mode only.

Total Team Workload is a total sum of scheduled hours for the whole team in a current week. The value changes when switching the calendar view. Showing how much work is scheduled on a person

Total Team Availability is a total sum of free hours on when the team members are open for any planned work. 

...

showing the current person's availability, not actual workload

...

negative number means that a person is overloaded for -N hours

...

0 means that a person is fully busy and is not availability for any upcoming work

...

Table of Contents
minLevel1
maxLevel6
outlinefalse
typelist
printablefalse

(question) Frequently Asked Question. Read more.

📰 Helpful tips in our Blog.

📬 Questions? Contacts Us.

🤝 Contact details for Solution partners.

Search doсumentation

Live Search
spaceKeyAC
placeholderSearch doсumentation...